Breightmet Health Centre

This scheme involved the refurbishment and alteration to create four bookable treatment rooms, a consultation room, store room, waiting and ancillary area.
CLIENT
SIZE
DATE COMPLETED
September 2022
VALUE
£330k
ARCHITECT
SUSTAINABILITY

Overview

Eric Wright Building Consultancy acted as lead consultant, contract administrators and project managers for the scheme, from inception to completion.

This scheme, delivered on time and to budget within an operating health over an 11 week programme and was completed in September 2022 with minimal snags.

Eric Wright Building Consultancy (EWBC) began work on this project in 2020 and managed the project to completion, within the set budget and timeframes. This was a direct award through the LIFT Co framework partnership. The project involved the internal alteration and refurbishment to existing ground floor minor ops and changing areas.

EWBC lead the stakeholder engagement from inception to completion, working closely with our client Combined Health Partnerships (CHP).

Initial designs options were reviewed a preferred option identified. This was than developed into a detail design, in conjunction with the service providers.

The scheme involved complex stakeholder engagement through LIFT Co, CHP, CCG and local service units.

A competitive exercise with proposed sub-consultants was undertaken to ensure value was driven through the consultant supply chain led by EWBC. This then enabled cost transparency
for the client. The scheme was designed and tendered using a modified version of JCT Intermediate Form 2016 contract due to the complex commercial relationship with the LIFT Co and SPV.

Our team was led by an experienced chartered building surveyor and supported by a building surveyor. The team undertook the project management, contract administration, lead consultant, principal designer role and all stakeholder engagement for the project. The appointed design team encompassed architect, MEP and structural engineers with the project management, contract administration and principal designer roles being undertaken in house by EWBC.

 

The early engagement of the design team resulted in all parties understanding the developed brief, cost plan and risks associated with the project but importantly resulting in programme and cost control throughout the project.

KEY FACTS

  • Value of scheme was £330,229
  • Contract JCT Intermediate Form 2016
  • with Contractors Design
  • Duration 11 weeks
  • Building regulations approval
  • Planning negotiations and submission
  • HTM and HBN compliant
  • Lead consultant
  • Contract administration
  • Project management
  • Principal Designer

KEY STAKEHOLDERS

  • Combined Health Partnerships (CHP)
  • One Partnership
  • Local Service Units
  • Lead consultant, project managers and contract administration – Eric Wright Building Consultancy
  • Sub consultant employed: architect, mechanical and electrical, structural engineer
  • Contractor EWC

Added Value

These works benefited the local community and health care professionals.
  • New bookable treatment and consultation rooms
  • 4 x treatment rooms
  • 1 x consultation rooms
  • Store and ancillary spaces crated
  • Refurbished areas including patient waiting and reception
  • High quality facility specification and output to meet clinical needs
  • 100% HTM and HBN complaint, signed off by the Clinical Commissioning Group
  • 100% infection control requirements met in all treatment and clinical rooms
  • Tight cost control and programme management