North Beck Bridge, Northallerton

New Northallerton 900m link road and rail overbridge
CLIENT
Taylor Wimpey / Persimmon / North Yorkshire County Council
LOCATION
Northallerton
VALUE
£8.1m
FORM OF CONTRACT
NEC4 Option A

Overview

The new 900m long link road and 150m span weathering steel bridge connects two housing developments in Northallerton, North Yorkshire, forming a bypass taking traffic from the centre of Northallerton.

The project involved forming new highway approach embankments up to 15m in height, with new RC bridge abutments and twin piers founded on 20m long 900mm diameter CFA piles which, in turn, supported the four weathering steel beams and cast in-situ reinforced concrete deck.

The bridge spans the railway line between Northallerton and Teesside, therefore all works associated with the bridge required approvals from Network Rail.

The project was secured through an open tender heavily weighted towards quality with tenderers having to demonstrate their experience of working with Network Rail and bridge construction work. EWCE has held a Principal Contractors Licence with Network Rail since 2012. All temporary works for the piling and crane platforms had to undergo Network Rail’s stringent review and approvals process. We undertook CAT 3 temporary works designs and checks to facilitate these approvals. This included lifting close to and over Network Rail property with cranes up to 1000T in size and booking of possessions for works directly over the line.

The project involved extensive earthworks to form the new approach embankments by importing over 100,000m³ of granular material 15m in height, with band drains under the footprint, geotextile basal reinforcement, a drainage layer and extensive geotechnical monitoring during construction on the soft alluvium.

The works required strict controls and checks to ensure they had been constructed in accordance with the specification. The monitoring was installed to ensure we did not over-stress the underlying soft ground. We monitored the works on an ongoing basis and reported back to the client and their designer, AECOM to verify stability of the ground before progressing with subsequent earthworks phases.

The works also included the diversion of the North Beck (an EA Main River) and extensive flood alleviation works, attenuation ponds and landscaping.

The new weathering steel beams were supplied by Cleveland Bridge, who we appointed in Spring 2020 during the height of the pandemic. We met with numerous suppliers and eventually settled on Cleveland with their extensive experience of similar large scale structures and long established history in the region.

Design and detailing queries were all resolved in good time working with ourselves, Cleveland, AECOM (Client’s designer) and North Yorkshire County Council (adopting authority). Procurement of main beam materials progressed according to the programme we had agreed with Cleveland which allowed ordering of materials prior to any price increases.

We secured all other materials required to construct the bridge, aware that transportation was taking longer to arrange, and lead-in times for all materials were typically increasing across the industry.

Fabrication progressed whilst we were constructing the embankments and RC structures on site ready to accept them.

During this period, we developed and finalised our temporary works for the crane platforms, temporary trestles and temporary restraints for the structure. These were all submitted to, and approved by, Network Rail.

We worked with AECOM to allow the stringcourse falsework to be pre-erected on the beams, even though this was not allowed at tender stage. We verified the temporary stability of the beams and determined the amount of falsework that could be pre-erected. We modified the specified erection sequence to assist and de-risk site installation. Again, this was approved by AECOM and Network Rail.

Approximately 4 weeks before the main bridge lifts were due to take place, Cleveland Bridge went into administration. This had the potential to affect the programme and jeopardise the safe supply of the steel that we were already contracted with them to provide.

As part of our sub-contract and the main contract with the Client, we had already entered into an appropriate vesting agreement, thereby safeguarding the supply of the steel in such instances. Our site and commercial teams immediately ensured our steel was safeguarded. We visited Cleveland to verify the current stage of fabrication and identify what missing elements still needed to be provided. We engaged closely with Cleveland’s commercial representatives and the appointed administrators to ensure we safeguarded the supply and outlined our legal title to all materials.

We immediately contacted Cleveland’s supply chain and set up our own orders with their key suppliers, including;

  • Collets (transportation)
  • MJ Hughes (site erection, crane lift and temporary works)

We took on board the role of Cleveland to manage the remainder of the fabrication, temporary works and site installation. After our quick and decisive action the main bridge beam installations over the rail went ahead as planned albeit one week behind schedule on the weekend of Saturday, 18th September with no issues. Both sets of braced pairs were erected during the limited rail possession from 10.00pm Saturday to 8.00am Sunday. Subsequently, we installed the remaining steel thereby allowing the RC deck works to progress unhindered.

The site was registered with Considerate Constructors and achieved a Certificate of Excellence.

Key Challenges

  • Working adjacent to a live railway line and ensuring compliance with Network Rail procedures
  • Pedestrian, cyclists, traffic including commercial vehicles and public transport will be affected by the works in the immediate area
  • All works kept to a minimum disturbance level including the use of dust suppression techniques/equipment and reducing noise to a minimum
  • Diversion of an existing watercourse and associated environmental constraints
  • Working at height
  • Covid-19

Added Value

Liaison with Network Rail for the duration of the project to ensure compliance with their guidance for working adjacent to live railways.  We originated and developed all required temporary works design for the installation of the bridge adjacent to the live rail. This included submission of Cat III checks in line with NR approval periods to ensure programmed installation dates were met. Regular progress and possession planning meetings were held to coordinate the required night time, weekend possessions for lifting in the new bridge beams and follow on placement of in-situ concrete elements of the bridge deck.

Key sub-contractor for the supply and installation of the bridge beams, Cleveland Bridge UK, unfortunately went into administration three weeks before delivery of the completed beams to site.  This had the potential to place the entire project in jeopardy, however, we quickly engaged with the CBUK administrator and secured completion of manufacture and release of the beams.  Through rapid integration of the CBUK supply chain into our own, we coordinated delivery of the beams, completed the unfinished fabrication of various critical temporary bracing elements essential to the installation, and successfully lifted in the beams in line with the programmed Network Rail possessions.

We mitigated any client delays as existing overhead electricity lines had not been diverted prior to our works starting on site. This caused a 5.2 week delay early on in the project. We were able to reprogramme our works so that this did not affect the overall programme.

All existing excavated material was re-used in the permanent works embankment reconstruction to reduce off-site disposal.

Early contractor involvement allowed us to complete early supply chain engagement, so that we could collaborate on project risks, challenges and identify any client savings. In addition, this allowed us to start early engagement with Network Rail on the required possessions.

“We are delighted to see this road and bridge open to traffic and our residents. Today's opening of the link road and bridge represents a huge step forward for Northallerton in terms of improving travel around town and reducing congestion. This is a key piece of infrastructure and it is fantastic to see the bridge open”
Councillor Mark Robson
Leader of the District Council

Related Case Studies

Civil Engineering / Bridges
Civil Engineering / Bridges
Civil Engineering / Bridges
Civil Engineering / Bridges

Get in Touch

For all enquiries, please get in touch with the team here at Eric Wright.